Schedule
-
Selected Contractor for Phase I (Moorland Road to Lannon Road) – Musson
-
Approximate start date for Phase I – May 1st, 2012
Contractor is planning to start as early as possible relative to utility relocations
-
WE Energies (gas/electric) – relocation is complete. Electric poles will be removed after cable TV is removed from the poles.
-
Time Warner (cable TV) – relocation is expected to be completed by April 20, 2012
-
AT&T (telephone) – relocation is expected to be completed by April 30, 2012
Phase I (Lannon Drive to Moorland Road):
-
Spring 2012 – Roadway Construction start
-
November 2012 – End General Construction
-
Spring 2013 - Complete final pavement layer
Phase II (CTH Y to Lannon Drive):
-
30% plans complete
-
60% plans - Spring 2012
-
Right-of-way Acquisitions - Spring 2012
-
Final plans - Fall 2012
-
Construction - Spring 2013